Exhibit 300 (BY2009) - National Select Agent Registry (NSAR) (formerly SATERIS), Centers for Disease Control and Prevention
PART ONE
OVERVIEW
- 1. Date of Submission:
- 2008-02-04
- 2. Agency:
- 009
- 3. Bureau:
- 20
- 4. Name of this Capital Asset:
- CDC National Select Agent Registry (NSAR) (formerly SATERIS)
- 5. Unique Project Identifier:
- 009-20-01-03-01-0547-00
- 6. What kind of investment will this be in FY2009?
- Mixed Life Cycle
- 7. What was the first budget year this investment was submitted to OMB?
- FY2005
- 8. Provide a brief summary and justification for this investment, including a brief description of how this closes in part or in whole an identified agency performance gap.
- The purpose of the joint CDC/HHS and APHIS/USDA inter-agency NSAR program is to support Public Law 107-188 by providing a single shared national database of information about regulated entities for Select Agent (SA) Program. The investment includes system software design & development, integration of COTS products, maintenance of the hardware, software, and database. Initial performance gaps include: inadequate database to collect, enter, process and report this information to appropriate authorities. It was difficult to manage the information necessary to regulate the Select Agent program. This investment addresses the performance gaps. It supports PMA-EGov by minimizing data entry redundancy through a single national database shared by CDC/APHIS, will improve information sharing when we implement collaborative electronic inter-agency approvals and will be able to reduce reporting burden for the regulated community when they have ability to complete/submit registration forms electronically. NSAR successfully merged their two select agent customer-facing websites into one shared national system. HHS obtained an agency neutral domain name for their shared system which is in use and serves as a single portal for SA information and for obtaining electronic forms for entities. Improvements in data collection accuracy, efficiency, & reporting have contributed to significant program performance improvements. Key capabilities provided: joint SA system architecture, a robust database, user based access, user interface, query, routine/ad-hoc reports and letters, document tracking, audit trails Targeted performance & productivity improvements include: reduction in the number of days to complete/process registrations through improved data entry and reporting, reduction in data entry error and unifying efficient information flows between agencies, minimizing redundant activities, and the reduction of the reporting burdens on the entities in cases of overlap agents. NSAR is designed to provide collaborative e-government activities between HHS, USDA, and DOJ. The joint inter-agency secure NSAR will provide regulated community capability to electronically submit SA forms thereby increasing process time. The impact of not fully funding this investment would include the loss of CDC's capability to efficiently comply with the mandates of PL 107-188,inability to register entities in a timely fashion, and inefficient inter-agency collaborative activities.
- 9. Did the Agency's Executive/Investment Committee approve this request?
- yes
- 9.a. If "yes," what was the date of this approval?
- 2007-06-26
- 10. Did the Project Manager review this Exhibit?
- yes
- 11.a. What is the current FAC-P/PM certification level of the project/program manager?
- Mid/Journeyman-level
- 12. Has the agency developed and/or promoted cost effective, energy-efficient and environmentally sustainable techniques or practices for this project.
- no
- 12.a. Will this investment include electronic assets (including computers)?
- yes
- 12.b. Is this investment for new construction or major retrofit of a Federal building or facility? (answer applicable to non-IT assets only)
- no
- 13. Does this investment directly support one of the PMA initiatives?
- yes
- If yes, select the initiatives that apply:
Initiative Name Expanded E-Government
- 13.a. Briefly and specifically describe for each selected how this asset directly supports the identified initiative(s)? (e.g. If E-Gov is selected, is it an approved shared service provider or the managing partner?)
- Gaps: inadequate database to collect, enter, process, report, redundant data entry, collaborations with APHIS. Supports eGov: minimizes data entry redundancy through a single joint national db, information sharing through inter-agency e-communications, reduce reporting burden for regulated community with e-submissions. Performance/productivity improvements: reduce registration time, data entry/reporting, robust database, efficient inter-agency collaboration, reduce entity reporting burden.
- 14. Does this investment support a program assessed using the Program Assessment Rating Tool (PART)?
- no
- 15. Is this investment for information technology?
- yes
- 16. What is the level of the IT Project (per CIO Council's PM Guidance)?
- Level 3
- 17. What project management qualifications does the Project Manager have? (per CIO Council's PM Guidance)
- (1) Project manager has been validated as qualified for this investment
- 18. Is this investment identified as high risk on the Q4 - FY 2007 agency high risk report (per OMB memorandum M-05-23)?
- no
- 19. Is this a financial management system?
- no
- 20. What is the percentage breakout for the total FY2009 funding request for the following? (This should total 100%)
Area Percentage Hardware 4 Software 6 Services 88 Other 3
- 21. If this project produces information dissemination products for the public, are these products published to the Internet in conformance with OMB Memorandum 05-04 and included in your agency inventory, schedules and priorities?
- n/a
- 22. Contact information of individual responsible for privacy related questions.
Name Alice M. Brown Phone Number 770-488-8223 Title IT Security Project Manager Email AMBrown1@cdc.gov
- 23. Are the records produced by this investment appropriately scheduled with the National Archives and Records Administration's approval?
- yes
- 24. Does this investment directly support one of the GAO High Risk Areas?
- yes
SUMMARY OF SPEND
- 1. Provide the total estimated life-cycle cost for this investment by completing the following table. All amounts represent budget authority in millions, and are rounded to three decimal places. Federal personnel costs should be included only in the row designated Government FTE Cost, and should be excluded from the amounts shown for Planning, Full Acquisition, and Operation/Maintenance. The total estimated annual cost of the investment is the sum of costs for Planning, Full Acquisition, and Operation/Maintenance. For Federal buildings and facilities, life-cycle costs should include long term energy, environmental, decommissioning, and/or restoration costs. The costs associated with the entire life-cycle of the investment should be included in this report.
All amounts represent Budget Authority
Note: For the cross-agency investments, this table should include all funding (both managing partner and partner agencies).
Government FTE Costs should not be included as part of the TOTAL represented. Cost Type Py-1 & Earlier
-2006PY
2007CY
2008BY
2009Planning Budgetary Resources 0.000 0.036 0.037 0.038 Acquisition Budgetary Resources 13.546 3.177 3.340 3.000 Maintenance Budgetary Resources 6.450 3.369 4.000 4.160 Government FTE Cost 1.180 0.260 0.280 0.290 # of FTEs 10 2 2 2
- 2. Will this project require the agency to hire additional FTE's?
- yes
- 2.a. If "yes," how many and in what year?
- We would like to hire 1 FTE by 2009
- 3. If the summary of spending has changed from the FY2008 President's budget request, briefly explain those changes.
- A small across-the-board budget reduction for the current budget year, unrelated to investment performance, was directed by CDC with a relatively minor impact to scope and schedule.
PERFORMANCE
- Agencies must use the following table to report performance goals and measures for the major investment and use the Federal Enterprise Architecture (FEA) Performance Reference Model (PRM). Map all Measurement Indicators to the corresponding Measurement Area and Measurement Grouping identified in the PRM. There should be at least one Measurement Indicator for each of the four different Measurement Areas (for each fiscal year). The PRM is available at www.egov.gov. The table can be extended to include performance measures for years beyond FY 2009.
Row Fiscal Year Strategic Goal Supported Measurement Area Measurement Grouping Measurement Indicator Baseline Planned Improvement to the Baseline Actual Results 1 2005 S.O. 2.1 - Prevent the spread of infectious diseases Mission and Business Results Key Asset and Critical Infrastructure Protection Completed SA entity registrations within 180 days of receipt 5% in 180 days 10% in 180 days 10% in 180 days 2 2005 S.O. 2.4 - Prepare for and respond to natural and man-made disasters Customer Results Availability Total system up-time 90% >90% System deployment delayed - no results. 3 2005 S.O. 4.3 - Conduct and oversee applied research to improve health and well-being Processes and Activities Errors Data entry error rate 7-8% 5-6% System deployment delayed - no results. 4 2005 Effective Management of Human Capital/Information Technology/Resources Technology External Data Sharing Inter-agency electronic concurrence Manual process Convert to electronic System deployment delayed - no results. 5 2006 S.O. 2.1 - Prevent the spread of infectious diseases Mission and Business Results Key Asset and Critical Infrastructure Protection Completed SA entity registrations within 180 days of receipt 10% in 180 days 45% in 180 days The program met its intended goal. 6 2006 S.O. 2.4 - Prepare for and respond to natural and man-made disasters Customer Results Availability Total system up-time 90% >90% Currently exceeding 99% up-time 7 2006 S.O. 4.3 - Conduct and oversee applied research to improve health and well-being Processes and Activities Errors Data entry error rate 7-8% 6-7% Staff learning new system, progress being made. 8 2006 Effective Management of Human Capital/Information Technology/Resources Technology External Data Sharing Inter-agency electronic concurrence Manual process Convert to electronic System deployment delayed due to CDC ID proofing issues 9 2007 S.O. 2.1 - Prevent the spread of infectious diseases Mission and Business Results Key Asset and Critical Infrastructure Protection Completed SA entity registrations within 180 days of receipt 45% in 180 days 95% in 180 days The program Met its intended goal. 10 2007 S.O. 2.4 - Prepare for and respond to natural and man-made disasters Customer Results Availability Total system up-time 90% >90% Currently exceeding 99% up-time 11 2007 S.O. 4.3 - Conduct and oversee applied research to improve health and well-being Processes and Activities Errors Data entry error rate 6-7% 5-6% The program Met its intended goal. 12 2007 Effective Management of Human Capital/Information Technology/Resources Technology External Data Sharing Inter-agency electronic concurrence >60 days 45-60 days System deployment delayed due to CDC ID proofing issues 13 2008 S.O. 2.1 - Prevent the spread of infectious diseases Mission and Business Results Key Asset and Critical Infrastructure Protection Completed SA entity registrations within 180 days of receipt 95% in 180 days 45% in 120 days 14 2008 S.O. 2.3 - Promote and encourage preventive health care, including mental health, lifelong healthy behaviors, and recovery Customer Results Availability Total system up-time 90% >90% 15 2008 S.O. 4.3 - Conduct and oversee applied research to improve health and well-being Processes and Activities Errors Data entry error rate 5-6% 4-5% 16 2008 Effective Management of Human Capital/Information Technology/Resources Technology External Data Sharing Inter-agency electronic concurrence 45-60 days 30-45 days 17 2009 S.O. 2.1 - Prevent the spread of infectious diseases Mission and Business Results Key Asset and Critical Infrastructure Protection Completed SA entity registrations within 180 days of receipt 45% in 120 days 95% in 120 days 18 2009 S.O. 2.3 - Promote and encourage preventive health care, including mental health, lifelong healthy behaviors, and recovery Customer Results Availability Total system up-time 90% >90% 19 2009 S.O. 4.3 - Conduct and oversee applied research to improve health and well-being Processes and Activities Errors Data entry error rate 4-5% 3-4% 20 2009 Effective Management of Human Capital/Information Technology/Resources Technology External Data Sharing Inter-agency electronic concurrence 30-45 days 20-30 days 21 2010 S.O. 2.1 - Prevent the spread of infectious diseases Mission and Business Results Key Asset and Critical Infrastructure Protection Completed SA entity registrations within 180 days of receipt 95% in 120 days 45% in 90 days 22 2010 S.O. 2.3 - Promote and encourage preventive health care, including mental health, lifelong healthy behaviors, and recovery Customer Results Availability Total system up-time 90% >90% 23 2010 S.O. 4.3 - Conduct and oversee applied research to improve health and well-being Processes and Activities Errors Data entry error rate 4% <4% 24 2010 Effective Management of Human Capital/Information Technology/Resources Technology External Data Sharing Inter-agency electronic concurrence 20-30 days 15-20 days 25 2011 S.O. 2.1 - Prevent the spread of infectious diseases Mission and Business Results Key Asset and Critical Infrastructure Protection Completed SA entity registrations within 180 days of receipt 45% in 90 days 95% in 90 days 26 2011 S.O. 2.3 - Promote and encourage preventive health care, including mental health, lifelong healthy behaviors, and recovery Customer Results Availability Total system up-time 90% >90% 27 2011 S.O. 4.3 - Conduct and oversee applied research to improve health and well-being Processes and Activities Errors Data entry error rate 3-4% <4% 28 2011 Effective Management of Human Capital/Information Technology/Resources Technology External Data Sharing Inter-agency electronic concurrence 15-20 days <15 days 29 2012 S.O. 2.1 - Prevent the spread of infectious diseases Mission and Business Results Key Asset and Critical Infrastructure Protection Completed SA entity registrations within 180 days of receipt 45% in 90 days 95% in 90 days 30 2012 S.O. 2.3 - Promote and encourage preventive health care, including mental health, lifelong healthy behaviors, and recovery Customer Results Availability Total system up-time 90% >90% 31 2012 S.O. 4.3 - Conduct and oversee applied research to improve health and well-being Processes and Activities Errors Data entry error rate 3-4% <4% 32 2012 Effective Management of Human Capital/Information Technology/Resources Technology External Data Sharing Inter-agency electronic concurrence 45% in 90 days <15 days 33 2013 S.O. 2.1 - Prevent the spread of infectious diseases Mission and Business Results Key Asset and Critical Infrastructure Protection Completed SA entity registrations within 180 days of receipt 45% in 90 days 95% in 90 days 34 2013 S.O. 2.3 - Promote and encourage preventive health care, including mental health, lifelong healthy behaviors, and recovery Customer Results Availability Total system up-time 90% >90% 35 2013 S.O. 4.3 - Conduct and oversee applied research to improve health and well-being Processes and Activities Errors Data entry error rate 3-4% <4% 36 2013 Effective Management of Human Capital/Information Technology/Resources Technology External Data Sharing Inter-agency electronic concurrence 45% in 90 days <15 days
Enterprise Architecture
- 1. Is this investment included in your agency's target enterprise architecture?
- yes
- 2. Is this investment included in the agency's EA Transition Strategy?
- yes
- 2.a. If yes, provide the investment name as identified in the Transition Strategy provided in the agency's most recent annual EA Assessment.
- CDC National Select Agent Registry (NSAR)
- 3. Is this investment identified in a completed (contains a target architecture) and approved segment architecture?
- no
- 4. Identify the service components funded by this major IT investment (e.g., knowledge management, content management, customer relationship management, etc.). Provide this information in the format of the following table. For detailed guidance regarding components, please refer to http://www.whitehouse.gov/omb/egov/.
Component: Use existing SRM Components or identify as NEW. A NEW component is one not already identified as a service component in the FEA SRM.
Reused Name and UPI: A reused component is one being funded by another investment, but being used by this investment. Rather than answer yes or no, identify the reused service component funded by the other investment and identify the other investment using the Unique Project Identifier (UPI) code from the OMB Ex 300 or Ex 53 submission.
Internal or External Reuse?: Internal reuse is within an agency. For example, one agency within a department is reusing a service component provided by another agency within the same department. External reuse is one agency within a department reusing a service component provided by another agency in another department. A good example of this is an E-Gov initiative service being reused by multiple organizations across the federal government.
Funding Percentage: Please provide the percentage of the BY requested funding amount used for each service component listed in the table. If external, provide the funding level transferred to another agency to pay for the service. Row Agency Component Name Agency Component Description Service Type Component Reused Component Name Reused UPI Internal or External Reuse? Funding % 1 Query Defines the set of capabilities that support retrieval of records that satisfy specific query selection criteria. Search Query No Reuse 15 2 Inbound Correspondence Management Defines the set of capabilities that manage externally initiated communication between an organization and its stakeholders. Routing and Scheduling Inbound Correspondence Management No Reuse 15 3 Outbound Correspondence Management Defines the set of capabilities that manage internally initiated communication between an organization and its stakeholders. Routing and Scheduling Outbound Correspondence Management No Reuse 15 4 Information Retrieval Defines the set of capabilities that allow access to data and information for use by an organization and its stakeholders. Knowledge Management Information Retrieval No Reuse 15 5 Data Integration Defines the set of capabilities that support the organization of data from separate data sources into a single source using middleware or application integration and the modification of system data models to capture new information within a single system. Development and Integration Data Integration No Reuse 10 6 Change Management Defines the set of capabilities that control the process for updates or modifications to the existing documents, software or business processes of an organization. Management of Processes Change Management No Reuse 10 7 Reservations / Registration Defines the set of capabilities that allow electronic enrollment and confirmations for services. Customer Initiated Assistance Reservations / Registration No Reuse 20
- 5. To demonstrate how this major IT investment aligns with the FEA Technical Reference Model (TRM), please list the Service Areas, Categories, Standards, and Service Specifications supporting this IT investment.
FEA SRM Component: Service Components identified in the previous question should be entered in this column. Please enter multiple rows for FEA SRM Components supported by multiple TRM Service Specifications.
Service Specification: In the Service Specification field, Agencies should provide information on the specified technical standard or vendor product mapped to the FEA TRM Service Standard, including model or version numbers, as appropriate. Row SRM Component >Service Area Service Category Service Standard Service Specification (i.e., vendor and product name) 1 Inbound Correspondence Management Service Access and Delivery Service Requirements Legislative / Compliance 36 CFR Part 1194 2 Reservations / Registration Service Platform and Infrastructure Delivery Servers Application Servers BEA WebLogic Platform 3 Inbound Correspondence Management Service Platform and Infrastructure Software Engineering Test Management Bobby 4 Inbound Correspondence Management Component Framework Security Supporting Security Services Check Point Firewall 5 Query Component Framework Data Management Reporting and Analysis Crystal Reports 6 Data Integration Service Interface and Integration Integration Middleware Distributed Component Object Model 7 Change Management Component Framework Business Logic Platform Dependent Documentum 8 Data Integration Service Platform and Infrastructure Software Engineering Integrated Development Environment Eclipse 9 Inbound Correspondence Management Component Framework Business Logic Platform Independent Enteprise Java Beans 10 Inbound Correspondence Management Service Interface and Integration Interoperability Data Format / Classification Extensible Markup Language (XML) 1.1 11 Inbound Correspondence Management Component Framework Presentation / Interface Static Display Hyper Text Markup Language 12 Inbound Correspondence Management Component Framework Presentation / Interface Static Display Hypertext Transfer Protocol with SSL 13 Inbound Correspondence Management Service Platform and Infrastructure Hardware / Infrastructure Wide Area Network (WAN) Integrated Services Digital Network (ISDN) - Core Aspects of Frame Protocol for Use with Frame Relay Bearer Service 14 Inbound Correspondence Management Service Platform and Infrastructure Support Platforms Platform Independent Java 2 Enterprise Edition 15 Inbound Correspondence Management Component Framework Data Management Database Connectivity Java DataBase Connectivity (JDBC) 16 Inbound Correspondence Management Component Framework Presentation / Interface Dynamic Server-Side Display Java Server Pages 17 Inbound Correspondence Management Component Framework Business Logic Platform Independent Java Servlet (JSR 53) 18 Inbound Correspondence Management Component Framework Business Logic Platform Independent JavaScript 19 Inbound Correspondence Management Service Platform and Infrastructure Software Engineering Integrated Development Environment jBuilder 20 Inbound Correspondence Management Service Platform and Infrastructure Software Engineering Test Management JProfiler 21 Information Retrieval Service Access and Delivery Service Transport Supporting Network Services Lightweight Directory Access Protocol 22 Inbound Correspondence Management Service Access and Delivery Service Transport Supporting Network Services Microsoft Active Directory 23 Reservations / Registration Service Platform and Infrastructure Delivery Servers Web Servers Microsoft Internet Information Services 24 Inbound Correspondence Management Service Platform and Infrastructure Database / Storage Database Microsoft SQL Server 25 Information Retrieval Service Platform and Infrastructure Support Platforms Platform Dependent Microsoft Windows 2000 26 Inbound Correspondence Management Service Access and Delivery Access Channels Web Browser Mozilla Firefox 27 Information Retrieval Service Access and Delivery Service Transport Supporting Network Services Multipurpose Internet Mail Extensions 28 Query Service Platform and Infrastructure Hardware / Infrastructure Peripherals Network Attached Storage, EMC 29 Data Integration Component Framework Data Management Database Connectivity Open Database Connectivity 30 Change Management Service Platform and Infrastructure Software Engineering Software Configuration Management Rational ClearQuest 31 Change Management Service Platform and Infrastructure Software Engineering Test Management Rational RequisitePro 32 Change Management Service Platform and Infrastructure Software Engineering Modeling Rational Rose 33 Inbound Correspondence Management Service Platform and Infrastructure Hardware / Infrastructure Peripherals Scanner 34 Inbound Correspondence Management Component Framework Security Certificates / Digital Signatures Secure Sockets Layer 35 Information Retrieval Component Framework Data Interchange Data Exchange SOAP 36 Query Service Platform and Infrastructure Database / Storage Database SQL 37 Query Service Interface and Integration Integration Middleware SQL 38 Information Retrieval Service Access and Delivery Service Transport Supporting Network Services T1 39 Information Retrieval Service Access and Delivery Service Transport Supporting Network Services T3 40 Inbound Correspondence Management Service Access and Delivery Service Transport Service Transport TCP/IP 41 Outbound Correspondence Management Component Framework Security Certificates / Digital Signatures The Transport Layer Security (TLS) Protocol Version 1.1 42 Change Management Service Platform and Infrastructure Database / Storage Storage Veritas NetBackup 43 Information Retrieval Service Access and Delivery Access Channels Other Electronic Channels Web Service 44 Information Retrieval Service Interface and Integration Interface Service Description / Interface Web Services Description Language (WSDL) 45 Inbound Correspondence Management Service Access and Delivery Access Channels Web Browser Windows Internet Explorer 6.0 46 Inbound Correspondence Management Service Interface and Integration Interoperability Data Types / Validation XML Schema 47 Inbound Correspondence Management Service Interface and Integration Interoperability Data Transformation XSL/T
- 6. Will the application leverage existing components and/or applications across the Government (i.e., FirstGov, Pay.Gov, etc)?
- yes
- 6.a. If yes, please describe.
- This investment leverages: Federal Health Architecture (FHA)
PART TWO
RISK
Answer the following questions to describe how you are managing investment risks.
- 1. Does the investment have a Risk Management Plan?
- yes
- 1.a. If yes, what is the date of the plan?
- 2006-08-04
- 1.b. Has the Risk Management Plan been significantly changed since last year's submission to OMB?
- no
- 3. Briefly describe how investment risks are reflected in the life cycle cost estimate and investment schedule:
- Schedule Risk from external dependencies is mitigated through the use of conservative milestone completion date estimates. Previous experience with integration efforts with both external agencies (CDC's Secure Data Network and USDA/APHIS) has provided historical context for adjusting internal schedule estimates with appropriate additional calendar time (adjusted at a macro level since we do not have a contractual relationship with either of the agencies with which we have schedule dependencies). Internal schedule risks are also accounted for through milestone estimate adjustments for historical experience, though are more directly tied to specific WBS tasks. The investment development effort is a complex project with multiple time-phased releases, however the major architectural elements are complete, integrated, and deployed; they no longer represent significant schedule risk. Initial Cost Risk is no longer a major factor since the investment has attained initial operational deployment and is 4 years into its contract. In addition, several major changes of direction for the program, driven both internally and through external direction (e.g., OMB direction to change development to a joint inter-agency system) make original cost estimates invalid. This investment is incrementally funded through annual exercise of option years to the contract base year (each year is fully funded/committed as funds are available). The original, modified, and current investment budget cost estimates are OMB approved. Lifecycle Cost Risk is estimated against the base year and 4 option years of the current contract, plus an additional estimated five years of use. Original Cost Benefit Analysis (CBA) figures present a Benefit-Cost Ratio of 1.64 with a payback period of approximately 7 years. As noted in the schedule risk and initial cost risk sections above, schedule adjustments have been made for both internal and external schedule risks, and associated cost estimates have been approved by OMB. The costs reported to OMB and used in the CBA include all development costs (DME) for the current contract period and estimated maintenance costs of the system/software for the projected five year follow-on contract (in line with the expected life cycle of the system). Earned Value Management information is reported monthly and overall investment cost and schedule variances are and expected to remain well below 10% for the remainder of the contract.
COST & SCHEDULE
- 1. Does the earned value management system meet the criteria in ANSI/EIA Standard 748?
- no
- 2. Is the CV% or SV% greater than ± 10%?
- no
- 3. Has the investment re-baselined during the past fiscal year?
- no